WaPA Project Planning
|
In this section we will provide information on project
planning, including the project schedule. The overall timescale is 18
months.
|
|
Work Package
|
Led by
|
Starts
|
Ends
|
WP1000
|
Review of SAR Surface Current Velocity Retrieval
|
NOC
|
13/12/12
|
20/03/13
|
WP2000
|
Validity of the Primary Scientific Products
|
Starlab
|
20/03/13
|
31/07/14
|
WP3000
|
Scatterometry
|
Ifremer
|
13/03/13
|
13/09/13
|
WP4000
|
Potential Secondary Products
|
Starlab
|
13/12/13
|
31/07/14
|
WP5000
|
Synergistic Instrument Data
|
NOC
|
13/03/14
|
31/10/14
|
WP6000
|
Project Management
|
SatOC
|
13/12/12
|
31/10/14
|
|