SCOOP Planning
|
In this section we will provide information on
project
planning, including the project schedule. The overall timescale is 2
years.
|
|
Work
Package
|
Led
By
|
Starts
|
Ends
|
WP1000
|
Scientific Requirements Consolidation
|
NOC
|
Oct '15
|
Jan '16
|
WP2000
|
Data Management
|
SatOC
|
Dec '15
|
May '17
|
WP3000
|
Doppler Stack Processing
|
isardSAT
|
Jan '16
|
Apr '17
|
WP4000
|
Echo Modelling / Retracking
|
Starlab
|
Jan '16
|
Apr '17
|
WP5000
|
Open Ocean Study
|
CLS
|
Jan '16
|
May '19
|
WP6000
|
Coastal Zone Study
|
NOC
|
Jan '16
|
Sep '19
|
WP7000
|
Wet Troposphere Model
|
U Porto
|
Jan '16
|
Apr '17
|
WP8000
|
Outreach, and Roadmap
|
SatOC
|
Oct '15
|
Sep '19
|
WP9000
|
Project Management
|
SatOC
|
Oct '15
|
Sep '19
|
|